Contract Agreement Amount

Rs. 46,58,933

Physical Progress

99.95%

Financial Progress

88.99%

Remaining Payment

Rs. 11

Roadway Excavation and Gabion wall on Naumula-Suchadada-Juni Road (Ch. 0+000 to 4+000Km), Dailekh

Office: सडक डिभिजन, सुर्खेत (33)

Fiscal Year: 076-77

99.95%

Contract Date: 1-Nov-19

Start Date: 1-Nov-19

Completion Date: 12-Apr-2020 (EOT Not Done)

Project Description

No description available.