Contract Agreement Amount
Rs. 91,96,834
Physical Progress
89.17%
Financial Progress
88.90%
Remaining Payment
Rs. 11
Construction Of Drain works along Morang Biratnagar 11 Alka Tole Deurali Marg Drain Sahit Kalopatre, Biratnagar 5 Radharaman Marg Tatha Budhihari Chowk Barju Simana Keshaliya Nadi Duhabi Sunsari Sadak, Morang and Ban Karyalaya Aasan Tole Prabesh Marg Hudai Rani Biratnagar 6 lane Jodne Sadak, Morang
Office: डिभिजन सडक कार्यालय, मोरङ (14)
Fiscal Year: 079-80
Contract Date: 27-Nov-22
Start Date: 28-Nov-22
Completion Date: 30-Jun-2023 (EOT Done)
Project Description
No description available.