Contract Agreement Amount
Rs. 61,93,437
Physical Progress
60.00%
Financial Progress
88.66%
Remaining Payment
Rs. 11
Recurrent Maintenance Work along Rapti Rajmarg (Chordanda, Boarder of Dang and Salyan District-Khulapass Section Ch.km 46+600 to km 135+00) in Salyan District
Office: सडक डिभिजन, दाङ्ग (31)
Fiscal Year: 075-76
Contract Date: 18-Nov-18
Start Date: 18-Nov-18
Completion Date: 16-May-2019 (EOT Done)
Project Description
No description available.