Contract Agreement Amount
Rs. 1,01,55,733
Physical Progress
0.00%
Financial Progress
88.38%
Remaining Payment
Rs. 11
Upgrading and Improvement works on Dharedhunga-Aarubutta-Ghormare-Thamu-Rabesi-Supa Deurali Road, Arghakhanchi
Office: सडक डिभिजन, कपिलवस्तु (29)
Fiscal Year: 078-79
Contract Date: 14-Jan-22
Start Date: 14-Jan-22
Completion Date: 10-Oct-2022 (EOT Done)
Project Description