Contract Agreement Amount

Rs. 1,87,29,028

Physical Progress

100.00%

Financial Progress

88.37%

Remaining Payment

Rs. 11

Road Construction Works on Basai Fatai Matiya Bandtal Khiriya Butabari Belauri Daiji Road, Kanchanpur

Office: सडक डिभिजन, कञ्चनपुर (34)

Fiscal Year: 074-75

100.00%

Contract Date: 12-Apr-18

Start Date: 12-Apr-18

Completion Date: 08-Feb-2020 (EOT Done)

Project Description

No description available.