Contract Agreement Amount

Rs. 2,96,83,274

Physical Progress

57.00%

Financial Progress

88.20%

Remaining Payment

Rs. 11

Construction of Bire Khola Bridge (RCC1X20m), Nuwakot

Office: गल्छी त्रिशुली मैलुङ्ग स्याफ्रुवेशी रसुवागढी सडक योजना, विदुर नुवाकोट (83)

Fiscal Year: 076-77

57.00%

Contract Date: 11-Nov-20

Start Date: 11-Nov-20

Completion Date: 08-Apr-2022 (EOT Not Done)

Project Description

No description available.