Contract Agreement Amount

Rs. 59,14,454

Physical Progress

0.00%

Financial Progress

0.00%

Remaining Payment

Rs. 100

Landslide Clearance and RCC Causeway Works on Byas Buddhasingh marga (Saranghat Ghumaune Sadak) (Chainage No. 0+000 to 7+000 km), Tanahun

Office: योजना तथा अनुगमन महाशाखा (भूवातावरण तथा सामाजिक शाखा) (4)

Fiscal Year: 080-81

0.00%

Contract Date: 9-Oct-23

Start Date: 9-Oct-23

Completion Date: 04-Apr-2024 (EOT Not Done)

Project Description

No description available.