Contract Agreement Amount
Rs. 59,14,454
Physical Progress
0.00%
Financial Progress
0.00%
Remaining Payment
Rs. 100
Landslide Clearance and RCC Causeway Works on Byas Buddhasingh marga (Saranghat Ghumaune Sadak) (Chainage No. 0+000 to 7+000 km), Tanahun
Office: योजना तथा अनुगमन महाशाखा (भूवातावरण तथा सामाजिक शाखा) (4)
Fiscal Year: 080-81
Contract Date: 9-Oct-23
Start Date: 9-Oct-23
Completion Date: 04-Apr-2024 (EOT Not Done)
Project Description
No description available.