Contract Agreement Amount
Rs. 20,17,96,568
Physical Progress
88.00%
Financial Progress
87.96%
Remaining Payment
Rs. 12
Construction of Sitalpur-Malangwa-Kharaiyatol Road, Sarlahi Package I (Ch 0+000 to 15+000)
Office: हर्कपुर ओखलढुङगा सडक योजना, ओखलढुङगा (62)
Fiscal Year: 072-73
Contract Date: 17-Jul-16
Start Date: 17-Jul-16
Completion Date: 13-Apr-2023 (EOT Done)