Contract Agreement Amount

Rs. 2,16,09,777

Physical Progress

88.00%

Financial Progress

87.91%

Remaining Payment

Rs. 12

Construction of RCC Bridge for Kajara Daha 2, Saptari along Rajbiraj Balan Hulaki Road

Office: हुलाकी राजमार्ग आयोजना, योजना कार्यालय, सुनसरी (64)

Fiscal Year: 071-72

88.00%

Contract Date: 14-Jul-15

Start Date: 28-Jul-15

Completion Date: 26-Oct-2024 (EOT Done)

Project Description

No description available.