Contract Agreement Amount
Rs. 2,16,09,777
Physical Progress
88.00%
Financial Progress
87.91%
Remaining Payment
Rs. 12
Construction of RCC Bridge for Kajara Daha 2, Saptari along Rajbiraj Balan Hulaki Road
Office: हुलाकी राजमार्ग आयोजना, योजना कार्यालय, सुनसरी (64)
Fiscal Year: 071-72
Contract Date: 14-Jul-15
Start Date: 28-Jul-15
Completion Date: 26-Oct-2024 (EOT Done)
Project Description
No description available.