Contract Agreement Amount

Rs. 45,33,216

Physical Progress

89.00%

Financial Progress

87.49%

Remaining Payment

Rs. 12

(Hume Pipe Culvert Works( at Ch 6+350,10+800,11+630) and Traffic Safety Works on Dharke Sitapaila Road (NH21).)

Office: यान्त्रिक कार्यालय, धनुषा (45)

Fiscal Year: 079-80

89.00%

Contract Date: 27-Apr-23

Start Date: 27-Apr-23

Completion Date: 10-Jul-2023 (EOT Not Done)

Project Description

No description available.