Contract Agreement Amount
Rs. 45,33,216
Physical Progress
89.00%
Financial Progress
87.49%
Remaining Payment
Rs. 12
(Hume Pipe Culvert Works( at Ch 6+350,10+800,11+630) and Traffic Safety Works on Dharke Sitapaila Road (NH21).)
Office: यान्त्रिक कार्यालय, धनुषा (45)
Fiscal Year: 079-80
Contract Date: 27-Apr-23
Start Date: 27-Apr-23
Completion Date: 10-Jul-2023 (EOT Not Done)
Project Description
No description available.