Contract Agreement Amount
Rs. 6,29,39,910
Physical Progress
90.00%
Financial Progress
87.46%
Remaining Payment
Rs. 12
Periodic Maintenance of Mahakali Highway (Ch. 29+000 to 68+000)
Office: सडक डिभिजन, कञ्चनपुर (34)
Fiscal Year: 073-74
Contract Date: 8-Feb-17
Start Date: 8-Feb-17
Completion Date: 29-Jun-2017 (EOT Not Done)