Contract Agreement Amount

Rs. 7,47,85,714

Physical Progress

7.47%

Financial Progress

87.23%

Remaining Payment

Rs. 12

Road Protection Work along Karnali Highway Hulma Bazaar to Gairigaun section (Ch 139+300 to 147+000), Kalikot

Office: सडक डिभिजन, वांके (32)

Fiscal Year: 079-80

7.47%

Contract Date: 7-Jun-23

Start Date: 7-Jun-23

Completion Date: 20-Aug-2024 (EOT Done)

Project Description

No description available.