Contract Agreement Amount

Rs. 4,78,06,003

Physical Progress

0.00%

Financial Progress

0.00%

Remaining Payment

Rs. 100

Khir Khauka Khola Bridge (1x15mRCC) Along Rajbiraj Chhinmasta Road

Office: डिभिजन सडक कार्यालय, चितवन (20)

Fiscal Year: 078-79

0.00%

Contract Date: 17-Oct-22

Start Date: 17-Oct-22

Completion Date: 23-Mar-2024 (EOT Not Done)

Project Description

No description available.