Contract Agreement Amount
Rs. 76,34,60,000
Physical Progress
89.00%
Financial Progress
87.00%
Remaining Payment
Rs. 13
BBPCU-DB-072/073-013 Design and Build of Bagmati River Bridge Piprabazar Rautahat
Office: पुल योजना पूर्वी क्षेत्र सेक्टर नं. १, धरान, सुनसरी (218)
Fiscal Year: 072-73
Contract Date: 12-Jul-16
Start Date: 12-Jul-16
Completion Date: 20-Mar-2025 (EOT Done)