Contract Agreement Amount
Rs. 2,75,43,359
Physical Progress
100.00%
Financial Progress
86.90%
Remaining Payment
Rs. 13
Construction of RCC Bridge for Bhaluwahi Khola, Saptari along Rajbiraj Kanchanpur Hulaki Road
Office: हुलाकी राजमार्ग आयोजना, योजना कार्यालय, सुनसरी (64)
Fiscal Year: 071-72
Contract Date: 13-Jul-15
Start Date: 29-Jul-15
Completion Date: 15-Dec-2022 (EOT Done)
Project Description
No description available.