Contract Agreement Amount

Rs. 63,89,88,885

Physical Progress

99.00%

Financial Progress

86.57%

Remaining Payment

Rs. 13

Dolakha Singati Road Project

Office: आयोजना निर्देशनालय, ए.डि.वि., विशालनगर, काठमाण्डौ (77)

Fiscal Year: 074-75

99.00%

Contract Date: 21-Aug-16

Start Date: 26-Sep-16

Completion Date: 31-Mar-2020 (EOT Done)

Project Description

No description available.