Contract Agreement Amount
Rs. 23,72,67,768
Physical Progress
98.73%
Financial Progress
86.51%
Remaining Payment
Rs. 13
Road Upgrading works along Holeri-Gwarkhola-Tulsipur Road (CH0+000 to 10+000) in Rolpa Distirct .
Office: डिभिजन सडक कार्यालय, ललितपुर (23)
Fiscal Year: 078-79
Contract Date: 26-Jun-22
Start Date: 26-Jun-22
Completion Date: 26-Aug-2024 (EOT Not Done)
Project Description
No description available.