Contract Agreement Amount

Rs. 23,72,67,768

Physical Progress

98.73%

Financial Progress

86.51%

Remaining Payment

Rs. 13

Road Upgrading works along Holeri-Gwarkhola-Tulsipur Road (CH0+000 to 10+000) in Rolpa Distirct .

Office: डिभिजन सडक कार्यालय, ललितपुर (23)

Fiscal Year: 078-79

98.73%

Contract Date: 26-Jun-22

Start Date: 26-Jun-22

Completion Date: 26-Aug-2024 (EOT Not Done)

Project Description

No description available.