Contract Agreement Amount
Rs. 33,68,83,278
Physical Progress
86.00%
Financial Progress
85.94%
Remaining Payment
Rs. 14
Extension of Karmanasha Khola-Harisiddhi-Godawari Road (Ch. 4+150 to 7+600)
Office: काठमाण्डौ उपत्यका सडक विस्तार आयोजना, काठमाण्डौ (214)
Fiscal Year: 073-74
Contract Date: 14-Jul-17
Start Date: 14-Jul-17
Completion Date: 13-Apr-2022 (EOT Done)
Project Description
No description available.