Contract Agreement Amount
Rs. 38,81,920
Physical Progress
85.00%
Financial Progress
85.62%
Remaining Payment
Rs. 14
Construction of RCC Retaining Wall, Masonary Works Replacement of Expansion Joints and Maintenance of Steel Railings along E/W Highway (270+900, 275+500, 281+500, 281+900, 258+600
Office: पच्चिमाञ्चल क्षेत्रिय सडक निर्देशनालय, पोखरा (9)
Fiscal Year: 079-80
Contract Date: 26-Dec-22
Start Date: 26-Dec-22
Completion Date: 10-Jul-2023 (EOT Not Done)
Project Description
No description available.