Contract Agreement Amount
Rs. 1,08,69,680
Physical Progress
85.57%
Financial Progress
85.57%
Remaining Payment
Rs. 14
Roadway Improvement works on Bi.Na.Pa 14 Gadi barahatal ka.pa. atntargat kalyankadh Chhapree dobata Rekcha Danras Benighat sadak(0+000-9+720)km,Surkhet
Office: सडक डिभिजन, सुर्खेत (33)
Fiscal Year: 076-77
Contract Date: 30-Jun-20
Start Date: 30-Jun-20
Completion Date: 12-Feb-2021 (EOT Not Done)
Project Description
No description available.