Contract Agreement Amount

Rs. 1,08,69,680

Physical Progress

85.57%

Financial Progress

85.57%

Remaining Payment

Rs. 14

Roadway Improvement works on Bi.Na.Pa 14 Gadi barahatal ka.pa. atntargat kalyankadh Chhapree dobata Rekcha Danras Benighat sadak(0+000-9+720)km,Surkhet

Office: सडक डिभिजन, सुर्खेत (33)

Fiscal Year: 076-77

85.57%

Contract Date: 30-Jun-20

Start Date: 30-Jun-20

Completion Date: 12-Feb-2021 (EOT Not Done)

Project Description

No description available.