Contract Agreement Amount
Rs. 87,14,707
Physical Progress
0.00%
Financial Progress
85.54%
Remaining Payment
Rs. 14
Contruction of Rigid Pavement structures on Maure- Tripurakot Road, Dolpa (Package 2)
Office: डिभिजन सडक कार्यालय, चौरजहारी (181)
Fiscal Year: 076-77
Contract Date: 10-Jul-20
Start Date: 18-Jul-20
Completion Date: 13-Apr-2021 (EOT Not Done)