Contract Agreement Amount

Rs. 1,26,65,043

Physical Progress

90.00%

Financial Progress

85.51%

Remaining Payment

Rs. 14

Periodic Mainanatance Works on Chyamasing Nala Banepa ( 6+970 - 9+900 ) Road

Office: सडक डिभिजन, भक्तपुर (24)

Fiscal Year: 076-77

90.00%

Contract Date: 26-Nov-19

Start Date: 26-Nov-19

Completion Date: 14-Mar-2022 (EOT Done)

Project Description

No description available.