Contract Agreement Amount
Rs. 2,96,96,767
Physical Progress
100.00%
Financial Progress
85.51%
Remaining Payment
Rs. 14
Construction of RCC Bridge with Pile Foundation in Aruwa Khola Bridge, Rautahat
Office: डिभिजन सडक कार्यालय, चन्द्रनिगाहापुर, गौर (176)
Fiscal Year: 072-73
Contract Date: 8-Apr-16
Start Date: 3-May-16
Completion Date: 08-Jul-2018 (EOT Done)
Project Description
No description available.