Contract Agreement Amount
Rs. 37,06,185
Physical Progress
0.00%
Financial Progress
85.49%
Remaining Payment
Rs. 14
Construction and Improvement of Malagiri Myalpokhari Duaneta Barbot Hulake Rangdal Chaphile Darling Road, Gulmi
Office: तम्घास सिमल्टारी प्युठान सडक आयोजना, गुल्मी (180)
Fiscal Year: 076-77
Contract Date: 21-Jun-20
Start Date: 21-Jun-20
Completion Date: 29-May-2023 (EOT Done)