Contract Agreement Amount

Rs. 6,17,25,535

Physical Progress

100.00%

Financial Progress

85.02%

Remaining Payment

Rs. 14

Construction of RCC Bridge over Pathariya River, Along Champapur Hattithala Jadepai Bhamka Road, Kanchanpur

Office: सडक डिभिजन, कञ्चनपुर (34)

Fiscal Year: 073-74

100.00%

Contract Date: 14-Jul-17

Start Date: 14-Jul-17

Completion Date: 11-Feb-2020 (EOT Done)

Project Description

No description available.