Contract Agreement Amount
Rs. 6,17,25,535
Physical Progress
100.00%
Financial Progress
85.02%
Remaining Payment
Rs. 14
Construction of RCC Bridge over Pathariya River, Along Champapur Hattithala Jadepai Bhamka Road, Kanchanpur
Office: सडक डिभिजन, कञ्चनपुर (34)
Fiscal Year: 073-74
Contract Date: 14-Jul-17
Start Date: 14-Jul-17
Completion Date: 11-Feb-2020 (EOT Done)
Project Description
No description available.