Contract Agreement Amount
Rs. 21,14,81,943
Physical Progress
0.00%
Financial Progress
84.89%
Remaining Payment
Rs. 15
Roadway improvement upto gravel standard including roadway widening/grade cutting and structure works at Ganeshchowk-Chiyobhanjyang Road Sector Chainaige (9+000-23+000), Paanchthar District
Office: Puspalal (Midhill) Road Project, Panchthar (273)
Fiscal Year: 072-73
Contract Date: 10-Mar-16
Start Date: 10-Mar-16
Completion Date: 26-Jun-2020 (EOT Done)
Project Description
No description available.