Contract Agreement Amount
Rs. 15,17,82,883
Physical Progress
89.00%
Financial Progress
84.87%
Remaining Payment
Rs. 15
Construction of Sitalpur-Malangwa-Kharaiyatol Road, Sarlahi Package III (Ch 30+000 to 40+370)
Office: हुलाकी राजमार्ग आयोजना, योजना कार्यालय, सुनसरी (64)
Fiscal Year: 072-73
Contract Date: 15-Jul-16
Start Date: 15-Jul-16
Completion Date: 14-Mar-2023 (EOT Done)
Project Description
No description available.