Contract Agreement Amount
Rs. 1,89,95,455
Physical Progress
0.00%
Financial Progress
84.83%
Remaining Payment
Rs. 15
Construction of RCC Bridge over Chauri Khola,Dolalghat Chauri Road,Guranse
Office: डिभिजन सडक कार्यालय, खुर्कोट (185)
Fiscal Year: 068-69
Contract Date: 6-Feb-12
Start Date: 6-Feb-12
Completion Date: 28-May-2020 (EOT Done)
Project Description
No description available.