Contract Agreement Amount
Rs. 84,23,362
Physical Progress
70.00%
Financial Progress
84.79%
Remaining Payment
Rs. 15
Roadway Excavation, Structural and Cross Drainage Works on Syaulibazar - Bardakot - Mityal Road [Furkechaur - Bardakot - Mityal Section], Palpa
Office: सडक डिभिजन, पाल्पा (27)
Fiscal Year: 076-77
Contract Date: 9-Jun-20
Start Date: 23-Jun-20
Completion Date: 11-Jan-2021 (EOT Done)
Project Description
No description available.