Contract Agreement Amount
Rs. 37,52,77,873
Physical Progress
0.00%
Financial Progress
84.69%
Remaining Payment
Rs. 15
MIDHLDNG3371384/073/074
Office: Puspalal (Midhill) Road Project, Dailekh (277)
Fiscal Year: 073-74
Contract Date: 31-May-17
Start Date: 21-Jun-17
Completion Date: 13-Apr-2022 (EOT Done)
Project Description