Contract Agreement Amount

Rs. 2,24,01,687

Physical Progress

0.00%

Financial Progress

84.61%

Remaining Payment

Rs. 15

Construction of RCC Bridge Over Phulping Khola (Jiri Sikri Hawa Sahare Road)

Office: डिभिजन सडक कार्यालय, दोलखा (18)

Fiscal Year: 072-73

0.00%

Contract Date: 8-Aug-16

Start Date: 8-Aug-16

Completion Date: 17-Aug-2019 (EOT Done)

Project Description

No description available.