Contract Agreement Amount
Rs. 2,24,01,687
Physical Progress
0.00%
Financial Progress
84.61%
Remaining Payment
Rs. 15
Construction of RCC Bridge Over Phulping Khola (Jiri Sikri Hawa Sahare Road)
Office: डिभिजन सडक कार्यालय, दोलखा (18)
Fiscal Year: 072-73
Contract Date: 8-Aug-16
Start Date: 8-Aug-16
Completion Date: 17-Aug-2019 (EOT Done)
Project Description
No description available.