Contract Agreement Amount

Rs. 3,46,10,075

Physical Progress

85.00%

Financial Progress

84.57%

Remaining Payment

Rs. 15

Extension & Improvement of Sadakpur Bauniya Jhabai Thapapur Road, Kailali

Office: सडक डिभिजन, कञ्चनपुर (34)

Fiscal Year: 071-72

85.00%

Contract Date: 15-Jul-15

Start Date: 15-Jul-15

Completion Date: 09-Jul-2020 (EOT Done)

Project Description

No description available.