Contract Agreement Amount
Rs. 5,36,94,490
Physical Progress
0.00%
Financial Progress
0.00%
Remaining Payment
Rs. 100
Kaligandaki Bridge, Rudrabeni (Syangja-Gulmi)
Office: सडक डिभिजन, पोखरा (26)
Fiscal Year: 067-68
Contract Date: 13-Jul-10
Start Date: 13-Jul-10
Completion Date: 12-Jan-2013 (EOT Not Done)
Project Description
No description available.