Contract Agreement Amount

Rs. 64,90,521

Physical Progress

100.00%

Financial Progress

84.48%

Remaining Payment

Rs. 15

Road widening & upgrading works at Patletar Annantalingeshwor Height Pokhari Thumka Lakuri Bhanjyang

Office: सडक डिभिजन, भक्तपुर (24)

Fiscal Year: 077-78

100.00%

Contract Date: 27-Apr-21

Start Date: 27-Apr-21

Completion Date: 09-Jul-2021 (EOT Not Done)

Project Description

No description available.