Contract Agreement Amount
Rs. 64,90,521
Physical Progress
100.00%
Financial Progress
84.48%
Remaining Payment
Rs. 15
Road widening & upgrading works at Patletar Annantalingeshwor Height Pokhari Thumka Lakuri Bhanjyang
Office: सडक डिभिजन, भक्तपुर (24)
Fiscal Year: 077-78
Contract Date: 27-Apr-21
Start Date: 27-Apr-21
Completion Date: 09-Jul-2021 (EOT Not Done)
Project Description
No description available.