Contract Agreement Amount
Rs. 3,38,90,463
Physical Progress
85.00%
Financial Progress
84.28%
Remaining Payment
Rs. 15
Construction Of RCC Multi Cell Box Bridge (3x10*x5) Over Jamuni River along Bashahiya Kabristan to Dhanauji Sadak, Dhanusha
Office: डिभिजन सडक कार्यालय, धनुषा (17)
Fiscal Year: 077-78
Contract Date: 24-Mar-21
Start Date: 24-Mar-21
Completion Date: 23-Apr-2023 (EOT Done)
Project Description
No description available.