Contract Agreement Amount
Rs. 4,01,60,512
Physical Progress
84.04%
Financial Progress
83.96%
Remaining Payment
Rs. 16
Rehabilitation Works along MRM (Mawa Khola to Koshi Barrage Section)
Office: डिभिजन सडक कार्यालय, मोरङ (14)
Fiscal Year: 078-79
Contract Date: 18-Apr-22
Start Date: 18-Apr-22
Completion Date: 17-Apr-2023 (EOT Not Done)
Project Description
No description available.