Contract Agreement Amount
Rs. 33,65,40,000
Physical Progress
85.00%
Financial Progress
83.89%
Remaining Payment
Rs. 16
Design & Build of Kakarhawa Khola Bridge, Gadhawa, Shantipur, Dang
Office: पुर्वाञ्चल क्षेत्रिय सडक निर्देशनालय, झापा (7)
Fiscal Year: 079-80
Contract Date: 26-Aug-20
Start Date: 26-Aug-20
Completion Date: 07-Feb-2024 (EOT Not Done)