Contract Agreement Amount
Rs. 5,36,64,069
Physical Progress
100.00%
Financial Progress
83.86%
Remaining Payment
Rs. 16
Construction of Prestressed Bridge (2*30m) over Sisne Khola along Lamahi-Ghorahi-Tulsipur Road in Dang District
Office: सडक डिभिजन, दाङ्ग (31)
Fiscal Year: 074-75
Contract Date: 23-Apr-18
Start Date: 23-Apr-18
Completion Date: 22-Sep-2019 (EOT Not Done)