Contract Agreement Amount

Rs. 5,36,64,069

Physical Progress

100.00%

Financial Progress

83.86%

Remaining Payment

Rs. 16

Construction of Prestressed Bridge (2*30m) over Sisne Khola along Lamahi-Ghorahi-Tulsipur Road in Dang District

Office: सडक डिभिजन, दाङ्ग (31)

Fiscal Year: 074-75

100.00%

Contract Date: 23-Apr-18

Start Date: 23-Apr-18

Completion Date: 22-Sep-2019 (EOT Not Done)

Project Description

No description available.