Contract Agreement Amount

Rs. 37,74,21,975

Physical Progress

100.00%

Financial Progress

83.79%

Remaining Payment

Rs. 16

upgrading of mrm birendra bazar yedukuwa 2073/74/UR009

Office: हुलाकी राजमार्ग निर्देशनालय​, काठमाण्डौ (230)

Fiscal Year: 073-74

100.00%

Contract Date: 9-Mar-17

Start Date: 24-Mar-17

Completion Date: 05-Nov-2020 (EOT Done)

Project Description

No description available.