Contract Agreement Amount
Rs. 8,49,96,688
Physical Progress
79.00%
Financial Progress
82.87%
Remaining Payment
Rs. 17
Danav River, Manmateriya - Naudihawa - Belawa Road
Office: सडक डिभिजन, वुटवल (28)
Fiscal Year: 070-71
Contract Date: 15-Jul-14
Start Date: 21-Jul-14
Completion Date: 13-Jan-2023 (EOT Done)