Contract Agreement Amount

Rs. 5,48,98,406

Physical Progress

100.00%

Financial Progress

82.86%

Remaining Payment

Rs. 17

Andheri Khola bridge Construction work Dharan Panbari Kerabari Sadak Dharan Sunsari

Office: पुल योजना पूर्वी क्षेत्र सेक्टर नं. १, धरान, सुनसरी (218)

Fiscal Year: 073-74

100.00%

Contract Date: 9-Jul-17

Start Date: 9-Jul-17

Completion Date: 14-Jan-2024 (EOT Done)

Project Description

No description available.