Contract Agreement Amount

Rs. 29,20,500

Physical Progress

0.00%

Financial Progress

82.81%

Remaining Payment

Rs. 17

Recurrent maintenanace works (Ch 132+000-205+000)

Office: डिभिजन सडक कार्यालय, जुम्ला (179)

Fiscal Year: 076-77

0.00%

Contract Date: 30-Sep-19

Start Date: 30-Sep-19

Completion Date: 05-Jan-2020 (EOT Not Done)

Project Description

No description available.