Contract Agreement Amount
Rs. 27,93,009
Physical Progress
82.58%
Financial Progress
82.61%
Remaining Payment
Rs. 17
Construction of Humepipe Culvert, Side Drain and Gravelling works on Masina Cheppang Barahataal-10, Surkhet
Office: डिभिजन सडक कार्यालय, दोलखा (18)
Fiscal Year: 079-80
Contract Date: 5-Feb-23
Start Date: 5-Feb-23
Completion Date: 15-Jun-2023 (EOT Not Done)
Project Description
No description available.