Contract Agreement Amount

Rs. 12,06,41,819

Physical Progress

85.00%

Financial Progress

82.56%

Remaining Payment

Rs. 17

swarna sagarmatha ring road (Ch. 0+000 - Ch 22+000)

Office: डिभिजन सडक कार्यालय, हर्कपुर, ओखलढुङगा (175)

Fiscal Year: 073-74

85.00%

Contract Date: 5-Jul-17

Start Date: 6-Jul-17

Completion Date: 04-Jul-2020 (EOT Not Done)

Project Description

No description available.