Contract Agreement Amount
Rs. 3,51,48,791
Physical Progress
90.00%
Financial Progress
82.34%
Remaining Payment
Rs. 17
Galwa/Jagadamba/Surma Sarobar J/V
Office: धनगढी-खुटिया-दिपायल-चैनपुर-उरैभन्ज्याङ्ग सडक योजना, बि.पी. नगर, डाेटी (294)
Fiscal Year: 078-79
Contract Date: 30-Jan-22
Start Date: 13-Feb-22
Completion Date: 14-Dec-2024 (EOT Done)
Project Description
No description available.