Contract Agreement Amount
Rs. 3,89,08,840
Physical Progress
0.00%
Financial Progress
82.21%
Remaining Payment
Rs. 17
अमसीता खोला पुल, हरिहरपुर गा.बि.स. वडा नं. ३ र ५, सप्तरी, सिराहा
Office: डिभिजन सडक कार्यालय, सिराहा (16)
Fiscal Year: 073-74
Contract Date: 17-Nov-17
Start Date: 1-Dec-17
Completion Date: 01-Mar-2019 (EOT Not Done)
Project Description
No description available.