Contract Agreement Amount
Rs. 23,57,68,494
Physical Progress
83.00%
Financial Progress
81.95%
Remaining Payment
Rs. 18
Extension of Chabhil-Jorpati-Sankhu Road (Ch. 9+000 to 11+460)
Office: काठमाण्डौ उपत्यका सडक विस्तार आयोजना, काठमाण्डौ (214)
Fiscal Year: 071-72
Contract Date: 30-Sep-15
Start Date: 30-Sep-15
Completion Date: 14-Jan-2023 (EOT Done)