Contract Agreement Amount

Rs. 3,35,62,045

Physical Progress

100.00%

Financial Progress

81.91%

Remaining Payment

Rs. 18

Construction of RCC Bridge over Bedkot River on Daijee Jogbudha Budar road (Daiji-Lipna Section) kanchanpur

Office: सडक डिभिजन, कञ्चनपुर (34)

Fiscal Year: 073-74

100.00%

Contract Date: 24-May-17

Start Date: 24-May-17

Completion Date: 24-May-2019 (EOT Not Done)

Project Description

No description available.