Contract Agreement Amount

Rs. 85,00,054

Physical Progress

70.00%

Financial Progress

81.70%

Remaining Payment

Rs. 18

हिमदुङ्ग/थोकर जे.भि.

Office: उत्तर दक्षिण (कालिगण्डकी करिडोर) लोकमार्ग योजना, पाल्पा (171)

Fiscal Year: 069-70

70.00%

Contract Date: 19-May-13

Start Date: 19-May-13

Completion Date: 12-Nov-2013 (EOT Done)

Project Description

No description available.