Contract Agreement Amount

Rs. 21,38,58,809

Physical Progress

80.00%

Financial Progress

81.65%

Remaining Payment

Rs. 18

Pacific-Jaljala JV

Office: उत्तर दक्षिण (कालिगण्डकी करिडोर) लोकमार्ग योजना, पाल्पा (171)

Fiscal Year: 075-76

80.00%

Contract Date: 9-Aug-19

Start Date: 7-Aug-21

Completion Date: 10-Jul-2023 (EOT Done)

Project Description

No description available.