Contract Agreement Amount
Rs. 21,38,58,809
Physical Progress
80.00%
Financial Progress
81.65%
Remaining Payment
Rs. 18
Pacific-Jaljala JV
Office: उत्तर दक्षिण (कालिगण्डकी करिडोर) लोकमार्ग योजना, पाल्पा (171)
Fiscal Year: 075-76
Contract Date: 9-Aug-19
Start Date: 7-Aug-21
Completion Date: 10-Jul-2023 (EOT Done)